Field trips (Check the site information out before the trip)
If there are problems with the schedule contact Jesus (Done-Pending). Also, the duties will be changing frequently and have a due date.
- Sunday, April 1 (departure 7:30 am) MRO, ABQ (Nature Center), and San Acacia (Alfalfa) [Hernan, Rodger, Kanayo, and Kim]
- Saturday, April 7 or Sunday April 8 (departure 7:00 am) Sevilleta DGPS survey [Hernan, Rodger, Kanayo, and Kim]
- Saturday, April 7 or Sunday April 8 (departure 7:00 am) To take down El Malpais site [Jesus, Hernan, Rodger, Kanayo, and Kim]
Recurring
- Check new LAS data:
- Infer which site visit occurred from field report. Download these new data from laptop, archive, and analyze on the desktop.
- Every Monday and Friday download remotely accessible data
- Update EDAC ftp site with new data
Other
- Email new biomass heat storage calculation to both Jans and Sung-Ho
- Debug cellular modems MRO (Cable 25ft is broken)
- Take down Scintec scintillometer at Alfalfa (All Group)
- EMRTC: XLAS setup (At the beginning of Summer)
- Estancia basin transect (Permit in process)
- POWER PROBLEMS
- Decrease transmitter power at all sites, such that signal strength = 50
- Set San Acacia Alfalfa to long range
Kim
- Get 135 lab organized: maps (due February 9)
- Take backpacks back to the gym (due ASAP)
- DGPS: Sevilleta
- Make a shape file with all the scintillometer sites (ask Jesus) (due February 20)
- Get batteries from ABQ, reset data loggers and recharge batteries
- Make a digital record of the field visit logs recollected until today and continue updating it (This is the new format FieldVisitLog.xls) ( due February 20)
- Call El Malpais people before April 7.
Rodger
- Get 135 lab organized: maps (due February 9)
- DGPS: Sevilleta
- Setup HOBOS at MRO
- Organize all DGPS data in a spreadsheet [X Y Z] (all the data is in a Folder named "Raghav" on the 135 Lab Computer) [Rodger and Hernan] (due February 15)
- Enter the old Sevilleta transects to the GPS (due February 9)
Hernan
- Setup HOBOS at MRO (Contact Rodger and Jesus)
- Download data from field laptop (goes to UCSD) (Ask Jesus how to do it) (due February 9)
- Get batteries from ABQ and reset data loggers
- Organize all DGPS data in a spreadsheet [X Y Z] (all the data is in a Folder named "Raghav" on the 135 Lab Computer) [Rodger and Hernan] (due February 15)
- Process data from last campaign and change demod reference values for realigned transects (contact Jesus; due February 15)
Jesus
- Get ECH2O-TE manual from http://www.decagon.com/manuals/ECHOTEman.pdf and obtain conversion equations to get physical values out of the voltages measured by the sensor (e.g. soil temperature in degrees Celsius) . Revise scint.m to compute and plot these physical values (due February 10)
- Test rain gauge on CR1000 in lab (ask Jan to send you a data logger program) (due February 15)
- Estimate new effective heights
- Modify scint.m for radiation and temperature analysis (due February 10)
- Process data from last campaign and change demod reference values for realigned transects (due February 15)
- Buy a new 25 pin serial cable for wireless connection at MRO